Amateur Extra Question E1B06
E1B: Station restrictions and special operations: restrictions on station location; general operating restrictions; spurious emissions; antenna structure restrictions; RACES operations
Which of the following additional rules apply if you are erecting an amateur station antenna structure at a site at or near a public use airport?
- You may have to notify the Federal Aviation Administration and register it with the FCC as required by Part 17 of the FCC rules (correct answer)
- You may have to enter the height above ground in meters, and the latitude and longitude in degrees, minutes, and seconds on the FAA website
- You must file an Environmental Impact Statement with the EPA before construction begins
- You must obtain a construction permit from the airport zoning authority per Part 119 of the FAA regulations
Correct answer: A, You may have to notify the Federal Aviation Administration and register it with the FCC as required by Part 17 of the FCC rules
Explanation
Section 97.15(a) says owners of certain antenna structures must notify the FAA and register with the FCC under Part 17. This applies to structures more than 60.96 m (200 feet) above ground, or located near or at a public use airport. The wording is "may have to" because Part 17 applies only when the structure's height and distance from the runway trigger it.
Why the other answers are wrong
- B, You may have to enter the height above ground in meters, and the latitude and longitude in degrees, minutes, and seconds on the FAA website: This describes a data-entry step, not the rule itself; Part 97 sends you to Part 17's FAA notification and FCC registration process.
- C, You must file an Environmental Impact Statement with the EPA before construction begins: No EPA Environmental Impact Statement is required; environmental review of amateur stations falls under FCC rules in §§1.1305-1.1319, per Section 97.13(a).
- D, You must obtain a construction permit from the airport zoning authority per Part 119 of the FAA regulations: FAA Part 119 covers certification of air carriers and commercial operators, not antenna permits, and no airport zoning permit is required by these rules.
Rule: §97.15